Williams Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/1997, Docket: RP96-387-000, Status: Effective
First Revised Sheet No. 229A First Revised Sheet No. 229A : Superseded
Superseding: Substitute Original Sheet No. 229A
GENERAL TERMS AND CONDITIONS
9. SCHEDULING, CURTAILMENT AND IMBALANCES (Cont'd)
Penalties will be levied by WNG against the Receiving Party
who controls the facilities into which gas is delivered. If
the Receiving Party does not have a transportation service
agreement with WNG, the nomination confirmation shall serve as
a contract between WNG and the Receiving Party for purposes of
paragraph (d) below.
(b) Under Receipts - During any period of daily balancing, if any
Delivering Party delivers a quantity of gas into WNG's system
at any Receipt Point, where at least 95% of volumes are
measured by electronic flow measurement equipment (EFM), less
than the nominations confirmed at such receipt point by such
Delivering Party, the difference between the confirmed
nomination and the actual quantity delivered shall be
considered Unauthorized Under Receipts and shall be subject to
daily balancing penalties as provided in (d) below. Actual
quantity delivered shall be determined by reference to
recorded EFM data. Penalties will be levied by WNG against
the Delivering Party who controls the facilities from which
gas is delivered. If the Delivering Party does not have a
transportation service agreement with WNG, the nomination
confirmation shall serve as a contract between WNG and the
Delivering Party for purposes of paragraph (d) below.
(c) On any day during a period of daily balancing, a Shipper
under Rate Schedule(s) TSS, STS, FTS, SFT, and/or FSS may be
subjected to daily balancing penalties by (1) exceeding any of
the production area or market area MDTQs or MDWQ, reduced if
necessary to reflect such items as capacity release, or
(2) depleting its available gas in storage. Any volumes taken
in excess of the production area or market area MDTQ's or MDWQ
or any storage withdrawals made after such Shipper's storage
account(s) is/are depleted, shall be considered Unauthorized
Capacity Overrun and shall be subject to daily balancing
penalties equal to 12 times the maximum monthly reservation
rate for the applicable area per Dth; provided, however, that
a 3% tolerance in excess of MDTQ shall be permitted. For any
Receiving Party who is also a Shipper under this paragraph,
any quantities taken in excess of MDQ at any delivery point
will be credited to any quantities taken in excess of that
party's MDTQ in total. Revenues received by WNG for