(d) An intra-day nomination will not be accepted if it would
curtail gas that is already flowing, regardless of its rate
schedule.
(e) Intra-day nominations cannot cause an agreement to exceed its
MDTQ.
9.3 Scheduling
(a) Receipts - WNG shall schedule gas at receipt points on its
transmission system in the following order:
First, firm Shippers using primary receipt points up to the
MDTQ of the service agreement,
Second, firm Shippers using secondary receipt points up to the
MDTQ of the service agreement,
Third, ITS and AOS Shippers based on rate paid, from highest
to lowest. ITS and AOS Shippers, whose gas is already flowing
at a discounted rate, may state, in advance, that they are
willing to pay the maximum rate to retain service in the event
WNG receives a higher bid.
(b) Deliveries - WNG shall schedule gas at delivery points on its
transmission system in the following order:
First, firm Shippers using primary delivery points up to the
MDTQ of the service agreement,
Second, firm Shippers using secondary delivery points up to
the MDTQ of the service agreement,