Carnegie Interstate Pipeline Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/1995, Docket: CP93-552-003, Status: Effective
Original Sheet No. 118 Original Sheet No. 118 : Effective
Superseding: Original Sheet No. 118
GENERAL TERMS AND CONDITIONS
(Continued)
18.2 (Continued)
established in Section
9.5(c). Where customers share the same
queue priority, scheduled service shall be
reduced on a pro rata basis, based upon the
nominations in effect at the time.
(2) Scheduled service under
CIPCO's firm service Rate Schedules FTS and
FGS on a pro rata basis, based upon
contract quantities.
(b) In the event any Customer desires to
relinquish voluntarily any rights to capacity to
which such Customer would be entitled under
CIPCO's curtailment order, such Customer shall
notify CIPCO of the quantities which are to be
relinquished, and CIPCO shall take such
relinquished quantities into account in
determining the total amount to be curtailed.
(c) In the event CIPCO is advised by a
Customer receiving service under Rate
Schedule(s) FTS or FGS that adjustment of the
curtailment level is necessary to avoid
irreparable injury to life or property including
environmental emergencies or to provide for
minimum plant protection for a duration
indicated by Customer ("emergency situation"),
then CIPCO shall adjust its curtailment of all
other Customers on a pro rata basis as necessary
to deliver the quantities required to avoid or
mitigate the emergency situation. While CIPCO
will make adjustments in curtailment promptly
upon notification by Customer, Customer must
provide CIPCO within twenty-four (24) hours of
Customer's notification to CIPCO a sworn
statement attesting to the following:
(1) All sources of gas supply
available to Customer, including peak-
shaving and storage, were and are being
utilized to the maximum extent possible
during the duration for which the emergency