GENERAL TERMS AND CONDITIONS
(Continued)
17.6 (continued)
b. The netting of imbalances does not relieve Customer
of the obligation to pay all transportation charges for the
quantity of gas actually delivered to Customer during the month.
17.7 Waiver
CIPCO shall not impose, and Customer shall not be liable
for, any penalty under this Section 17 for any imbalance
caused by CIPCO or as a result of an event of force majeure.
18. CAPACITY CURTAILMENT
18.1 Right to Curtail
In the event unexpected capacity limitations cause CIPCO
to be unable to deliver scheduled services, CIPCO shall have
the right to curtail, interrupt, or discontinue service under
Rate Schedule(s) FTS, FGS, ITS, or IGS in whole or in part on
all or a portion of its system from time to time and at any time: