Carnegie Interstate Pipeline Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1997, Docket: RP97-173-001, Status: Effective
Original Sheet No. 106A Original Sheet No. 106A : Effective
Superseding: Original Sheet No. 106A
GENERAL TERMS AND CONDITIONS
(Continued)
16. OPERATIONAL FLOW ORDERS
16.1 General
In the event CIPCO determines, in its sole
discretion, that in order to permit the continued
operation of all or part of its system a quantity of
gas received or delivered at any point or location on
its system must be increased or decreased, and that
such operating requirement cannot be accomplished
using the facilities and gas supply under CIPCO's
control in the time period necessary, CIPCO may issue
an operational flow order ("OFO") to Customer in
accordance with this Section 16. Such OFOs shall be
applied on a non-discriminatory basis at the
designated points on CIPCO's system at which action
is required.