15.2 (Continued)
(ii) The Intraday 1 Nomination
Cycle: 10:00 a.m. for nominations leaving
control of the nominating party; 10:15 a.m.
for receipt of nominations by CIPCO; 10:30
a.m. to send Quick Response; 1:00 p.m. for
receipt of completed confirmations by CIPCO
from upstream and downstream connected
parties; 2:00 p.m. for CIPCO to provide
scheduled quantities to affected shippers
and point operators, and to provide
scheduled quantities to bumped parties
(notice to bumped parties), (central clock
time on the gas day). Scheduled quantities
resulting from Intraday 1 Nomination should
be effective at 5:00 p.m. on gas day.