Carnegie Interstate Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/1995, Docket: CP93-552-003, Status: Effective

Original Sheet No. 53 Original Sheet No. 53 : Effective

Superseding: Original Sheet No. 53

GENERAL TERMS AND CONDITIONS

(Continued)

 

6.1 (Continued)

 

(d) Where the quantity of gas requires the

determination of heating value (Btu), a

recording calorimeter to continuously measure

and record the heating value (Btu) shall be

provided at a location which will measure the

Btu content of the gas delivered, or at a

mutually agreeable location unless alternative

heating value (Btu) determination methods are

mutually agreed upon by Customer and CIPCO.

 

6.2 Check Measurement Equipment

 

Customer may install, operate, and maintain, at

its own expense, such check measurement equipment as

it shall desire, provided that such equipment shall

be so installed as not to interfere with the

operation of other, including CIPCO's, measurement

equipment at or near the Delivery Point(s). CIPCO

shall have access to such check measurement equipment

at all reasonable hours, but the reading,

calibrating, and adjusting thereof and the changing

of charts shall be done only by Customer.

 

6.3 Access to Equipment and Records

 

Each party shall have the right to be present at

the time of any installing, reading, cleaning,

changing, repairing, inspecting, testing,

calibrating, or adjusting done in connection with the

other's measurement equipment used in measuring

deliveries hereunder. The records from such

measurement equipment shall remain the property of

their owner, but upon request each will submit to the

other its records and charts, together with

calculations therefrom, for inspection and

verification, subject to return within thirty (30)

days after receipt thereof.

 

6.4 Pressure Protection

 

Pressure regulation, pressure override, and

pressure relief valve or other pressure limiting

devices installed and operated by CIPCO at the

measuring station or near each primary or secondary

Delivery Point shall only be for the purpose of

operation and protection of CIPCO's measurement

equipment and CIPCO's facilities.