Carnegie Interstate Pipeline Company
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/1995, Docket: CP93-552-003, Status: Effective
Original Sheet No. 25 Original Sheet No. 25 : Effective
Superseding: Original Sheet No. 25
RATE SCHEDULE FMS
(Continued)
4. CURTAILMENT
4.1 Right to Curtail
In the event unexpected gas supply limitations
cause CIPCO to be unable to deliver to all Customers
receiving service under this Rate Schedule FMS the
quantities of gas CIPCO is obligated to deliver,
CIPCO shall have the right to curtail, interrupt, or
discontinue service under this Rate Schedule FMS in
whole or in part on all or a portion of its system
from time to time and at any time.
4.2 Priorities
Available gas supplies shall be allocated
proportionately among Customers receiving service
under this Rate Schedule FMS so as to fulfill,
whenever possible, each such Customer's requirements
in each of the priorities of use listed below.
CIPCO's deficiency of gas supplies shall be
apportioned among each such Customer beginning with
the lowest priority, then in sequence to the highest
priority, on the basis of the ratio of each such
Customer's requirements in the respective priority to
the total of all such Customers' requirements in the
same priority. Requirements in a higher priority
will not be curtailed until all requirements in the
lower priorities have been completely curtailed.
(a) Residential, small commercial (less
than 50 Dth on a peak day), schools, hospitals,
police protection, fire protection, sanitation
facility, or correctional facility, or any other
use determined to be a high-priority use under
Section 401(f)(2)(D) of the Natural Gas Policy
Act.
(b) Essential agricultural uses.
(c) Essential industrial process and
feedstock uses, including firm industrial
requirements for plant protection.
(d) All other requirements not specified
above.