RATE SCHEDULE IGS
INTERRUPTIBLE GATHERING SERVICE
1. AVAILABILITY
This Open-access Rate Schedule is available to any
Customer which has requested interruptible gathering
service pursuant to Section 9 of the General Terms and
Conditions of CIPCO's FERC Gas Tariff and, after review
and acceptance of such request by CIPCO, has entered into
a Service Agreement with CIPCO for service under Rate
Schedule IGS. Such Service Agreement shall be in the form
contained in CIPCO's FERC Gas Tariff, of which this Rate
Schedule IGS is a part.
2. APPLICABILITY AND CHARACTER OF SERVICE
2.1 Gathering service hereunder shall be
interruptible.
2.2 CIPCO shall receive into and transport through
CIPCO's gathering system quantities of natural gas up
to Customer's Maximum Daily Gathering Quantity
("MDGQ"), plus Applicable Shrinkage. Such MDGQ shall
be specified in the executed Service Agreement under
this Rate Schedule IGS. CIPCO shall transport and
deliver or cause to be transported and delivered on
behalf of Customer to the Delivery Point such
quantities tendered up to such Customer's MDGQ.
2.3 For the purposes of receipt, gas shall be deemed
to be received at any or all receipt points on
CIPCO's gathering system. The primary Delivery Point
for all such gas shall be the point at which gas is
delivered into CIPCO's transmission system at the
outlet side of the Waynesburg Compressor Station,
unless otherwise specified in the applicable Service
Agreement. Customer shall have secondary delivery
point capacity at all other delivery points on
CIPCO's gathering system, subject to capacity and
operational limitations.
2.4 Applicable Shrinkage is set forth in Section 2
of the General Terms and Conditions of CIPCO's FERC
Gas Tariff.