Carnegie Interstate Pipeline Company

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: / / , Docket: CP93-552-003, Status: Effective

Original Sheet No. 9 Original Sheet No. 9 : Effective

Superseding: Original Sheet No. 9

REVISED INITIAL DIRECT BILLING OF ACCOUNT NO. 191 COSTS

PURSUANT TO SECTION 31.3(b)

OF THE GENERAL TERMS AND CONDITIONS

 

Revised Remaining Total

Direct Bill Direct Bill Monthly

Customer Amount Amt.(Refund)

Amount 1/

 

Columbia Gas of Ohio, Inc.$ 635,358.10$415,133.74$ 51,891.72

 

Columbia Gas of Pa., Inc.$ 476,517.43$311,349.59$ 38,918.70

 

New Jersey Natural Gas Co.$ 857,732.75$(37,115.80) -0-

 

UGI Utilities, Inc. $ 317,679.05 $216,900.36$ 27,112.55

 

$2,287,287.33 $906,267.89$117,922.97

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/ Customer may elect to make payments of amounts billed

pursuant to an amortization of the total amount over a period

not exceeding eight months, commencing with the February 1,

1994 billing, plus carrying charges of amounts as yet

uncollected.