2. IMBALANCES
The actual physical flow at the Point of Interconnect each
month will be determined and communicated by AWP in writing as
soon as possible but in no case later than the tenth (10th)
Business Day of the month following the month in question.
Actual physical flows shall be determined pursuant to AWP's
then effective Federal Energy Regulatory Commission ("FERC")
Gas Tariff. Any Operational Imbalance shall be agreed to
within thirty (30) days of the date the Operational Imbalance
is agreed to in writing on the attached Exhibit "I" or within a
mutually agreeable longer period of time.
The parties shall use their best reasonable efforts to correct
any Operational Imbalance in a manner mutually agreed to by The
Parties.
All quantities of gas hereunder, received or delivered, to
correct an Operational Imbalance, shall be reported in thermal
units which are determined pursuant to AWP's then effective
FERC Gas Tariff.
3. SUSPENSION OF OBLIGATION
In the event that a capacity constraint occurs on either
Party's pipeline system which results in curtailment of
quantities through the Point of Interconnect, the Party on
whose system the constraint has occurred shall determine the
reallocation of quantities to the shippers. The confirmed
nominations shall be changed to reflect such reallocation of
capacity pursuant to Paragraph 1. above.
Notwithstanding anything to the contrary in this Agreement,
confirming nominations as actual physical flow and accounting
for the imbalances may be temporarily suspended in the event
that either Party discovers or anticipates that the physical
flow at the Point of Interconnect varies or will vary
significantly from the confirmed nominations due to
extraordinary circumstances such as significant interruption of
transportation service, severe cold weather, a hurricane or
some other event that significantly affects the gas supplies
available for delivery at the Point of Interconnect. Such
suspensions will be effective on the date verbal notice is
provided by the suspending Party's Gas Control personnel to the
other party's Gas Control personnel. Such verbal notice shall
be confirmed in writing no later than the second Business Day
following the day of desired suspension. Each