Arkansas Western Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/1993, Docket: CP92-570-005, Status: Effective
Original Sheet No. 62 Original Sheet No. 62 : Superseded
of reserves and deliverability characteristics of the
gas supply to be attached, the cost of the facilities,
operating and maintenance as well as administrative and
general expenses attributable to the facilities, the
revenues Transporter estimates will be generated as a
result of such construction, and the availability of
capital funds on terms and conditions acceptable to
Transporter. In estimating the revenues to be
generated, Transporter will evaluate the existence of
capacity limitations downstream of the facilities, the
marketability of the gas supplies, the location of the
markets for the gas supplies, the interruptible versus
the firm nature of the service for the attached gas
supplies, and other similar factors which impact
whether the available deliverability from the attached
gas supplies will actually be transported in a manner
that generates incremental benefits to Transporter.
d. All facilities installed by Transporter under this
Section 2.4 shall be owned and operated by Transporter.
3. DATA REQUIRED FOR VALID REQUEST FOR INTERRUPTIBLE TRANSPORTATION
3.1 All Shippers requesting interruptible transportation service
to commence on or after the effective date of this ITS Rate
Schedule must provide the information required by
Transporter's Service Request Form included in Transporter's
General Terms and Conditions in order to qualify for
interruptible transportation service. All such requests
shall be sent to Transporter at:
Arkansas Western Pipeline Company
4900 Woodway Drive
Suite 740
Houston, Texas 77056
Attention: Transportation Agent
A Request shall be considered valid only if it contains all
applicable information requested by Transporter's Service
Request Form.
3.2 The date that service is requested to commence shall be no
later than ninety (90) days from the date of the request or,
if construction of facilities is required, the date on which
all necessary governmental authorizations are received and
construction of any required facilities is completed.