Enbridge Pipelines (AlaTenn) Inc.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2001, Docket: GT01- 31-000, Status: Effective
Original Sheet No. 54 Original Sheet No. 54 : Effective
RATE SCHEDULE IT (continued)
Shipper's designee shown on Exhibit B to the IT Contract.
4.3 Transporter shall not be obligated to deliver gas pursuant to this
Rate Schedule to a Delivery Point that is operated by a Shipper
that has entered into an FT-SG Contract with Transporter unless
the FT-SG Shipper and the IT Shipper have first complied with the
provisions of Section 7 of Transporter's FT-SG Rate Schedule.
4.4 Transporter shall not be required under any circumstances to
deliver gas to any Delivery Point(s) where the total quantity of
gas scheduled for delivery on any day is less than that required
for the accurate measurement of quantities to be delivered.
4.5 Pressures: Shipper shall deliver gas to Transporter at the
pressure required from time to time to enable the gas to enter
Transporter's facilities at the Receipt Point. Transporter shall
deliver gas to Shipper or Shipper's designee at Transporter's line
pressure existing at the Delivery Point(s).
4.6 Uniform Quantities: Shipper shall deliver and receive gas in
uniform hourly quantities during any day with no significant
fluctuation.
5. RATE
5.1 Applicable Rates: The rates for service under this Rate Schedule
is the applicable Maximum IT rate shown on the effective Tariff
Sheet No. 4; provided, however, Transporter has the right at any
time and from time to time to adjust the rate applicable to any
transportation service upon notice to Shipper to any level not
less than the Minimum or more than the Maximum Rates established
for this Rate Schedule as set forth on the effective Tariff Sheet
No. 4.
Transporter shall file with the Commission the reports required
under Section 284.7 of the Commission's Regulations for any
adjustment below the Maximum Rates for service under this Rate
Schedule.