Enbridge Pipelines (AlaTenn) Inc.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2001, Docket: GT01- 31-000, Status: Effective
Original Sheet No. 52 Original Sheet No. 52 : Effective
RATE SCHEDULE IT (continued)
collectively referred to as "The Shipper") of a voluntary petition
in bankruptcy or the entry of a decree or order by a court having
jurisdiction in the premises adjudging The Shipper bankrupt or
insolvent. Insolvency, for purposes herein, shall also include
approval by any such court, as properly filed, of a petition
seeking reorganization, arrangement, adjustment or composition of
or in respect of The Shipper under the Federal Bankruptcy Act or
any other applicable federal or state law, or appointing a
receiver, liquidator, assignee, trustee, sequestrator (or other
similar official) of The Shipper or of any substantial part of its
property, or the ordering of the winding-up or liquidation of its
affairs, with said order or decree continuing unstayed and in
effect for a period of sixty (60) consecutive days.
3.3 (a) An IT Contract in the form included beginning at Tariff
Sheet No. 329, shall be executed by Shipper and Transporter
following Transporter's acceptance in writing of Shipper's
request for service and prior to commencement of service.
In the event the IT Contract is not executed and returned by
Shipper within thirty days after Transporter tenders the
contract, Transporter shall consider the request for service
invalid.
(b) If the gas to be transported is not for Shipper's system
supply, or its ultimate end use, then on or before the date
the IT Contract is executed Shipper shall (i) identify the
name of the corporate entity or entities which will
ultimately receive the gas to be transported and (ii)
provide verification that the identified ultimate recipients
have executed sales contracts related to the transportation
services to be provided under the IT Contract.
3.4 Shipper's IT Contract shall be terminated and Shipper's request
for service shall be deemed null and void if Shipper fails to
tender gas for transportation within fifteen days after the later
of: