Enbridge Pipelines (AlaTenn) Inc.

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2001, Docket: GT01- 31-000, Status: Effective

Original Sheet No. 38 Original Sheet No. 38 : Effective

 

RATE SCHEDULE FT-SG (continued)

 

 

be at a mutually agreeable interconnection between Transporter's

facilities and the facilities of the upstream pipeline system

providing service as shown in Exhibit A to the FT-SG Contract.

The total quantity specified at the Primary Receipt Point(s) must

equal the sum of the Contract Demand and Fuel and Losses

requirement set forth in Section 8 of this Rate Schedule.

Transporter shall not be required under any circumstances to

receive gas at any Receipt Point(s) where the total quantity of

gas scheduled for receipt on any day is less than that required

for the accurate measurement of quantities to be received.

 

4.2 Delivery Points: The Primary Delivery Point(s) for all gas

transported by Transporter under this Rate Schedule shall be at a

mutually agreeable interconnection between Transporter's

facilities and the facilities of Shipper or Shipper's designee as

shown in Exhibit B to the FT-SG Contract. The total quantity

specified at the Primary Delivery Point(s) must equal the Contract

Demand stated in the FT-SG Contract. Transporter shall not be

required under any circumstances to deliver gas at any Delivery

Point where the total quantity of gas scheduled for delivery in

any day is less than that required for the accurate measurement of

quantities to be delivered.

 

4.3 Change in Receipt and Delivery Point(s): Subject to availability

of Firm Capacity, Shipper may change the Primary Receipt or

Delivery Point(s) under its FT-SG Contract (including

redistributing the Contract Demand amount) on a monthly basis by

an amendment of Exhibits A and/or B to the FT-SG Contract. Such

amendment shall be reflected in an executed revision of Exhibits A

and/or B submitted to Transporter by the twentieth of the month

preceding the month for which the change is desired.

 

Subject to available capacity, Transporter will allow a change to

designated Receipt Point(s) at any time in the event of failure to

deliver committed gas supplies because of equipment failure,

compressor malfunction, freezing, or similar force majeure

conditions. Transporter will provide, via its Electronic Bulletin

Board ("EBB") notice