Midcoast Interstate Transmission, Inc.
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/1997, Docket: GT97- 71-000, Status: Effective
First Revised Sheet No. 49 First Revised Sheet No. 49 : Effective
Superseding: ORIGINAL SHEET NO. 49
RATE SCHEDULE IT (continued)
(a) Shipper's service commencement date established
pursuant to Section 3.1(c) of this Rate Schedule; or
(b) the date on which the IT Contract is executed by
Shipper, or
(c) the date on which Shipper is notified that any
facilities necessary to render the requested service
are ready for service.
Provided, however, (1) Shipper's failure to tender gas for
transportation shall be excused by an event of force
majeure as defined in Section 11 of the General Terms and
Conditions of Transporter's FERC Gas Tariff except that
temporary failure of gas supply due to factors other than
physical impairment of facilities shall not be excused, and
(2) Shipper's IT Contract shall be revalidated and given
full force and effect if Shipper (i) notifies Transporter
in writing within ninety (90) days after the date on which
the IT Contract is executed by Shipper of its intent to
transport gas pursuant to the IT Contract and (ii) tenders
gas for transportation within fifteen days after the date
Transporter receives the notice of intent. The notice of
intent shall constitute a new request for service for
purposes of scheduling priority.
4. DELIVERY AND RECEIPT POINTS; PRESSURES; UNIFORM QUANTITIES
4.1 Receipt Points: The Receipt Point(s) for all gas
transported by Transporter under this Rate Schedule shall
be at a mutually agreeable interconnection between
Transporter's facilities and the facilities of the
upstream pipeline system providing service as shown on
Exhibit A to the IT Contract. Transporter shall not be
required under any circumstances to receive gas at any
Receipt Point(s) where the total quantity of gas scheduled
for receipt on any day is less than that required for the
accurate measurement of quantities to be received.
4.2 Delivery Points: The Delivery Points(s) for all gas
transported by Transporter under this Rate Schedule shall
be at a mutually agreeable interconnection(s) between
Transporter's facilities and the facilities of Shipper or