5.5 Delivery Nominations and Scheduling (continued)
(3) The Intraday 1 Nomination Cycle on the Day of
Gas flow shall be as follows:
10:00 a.m. Nomination leaves control of the
nominating party.
10:15 a.m. Receipt of nomination by Transporter
(including from TTTSPs).
10:30 a.m. Transporter sends Quick Response.
1:00 p.m. Receipt of completed confirmations
by Transporter from upstream and
downstream connected parties.
2:00 p.m. Transporter provides scheduled
quantities to Shipper and point
operator, including notice to bumped
Shippers.
The effective time of scheduled quantities
resulting from a nomination submitted during the
Intraday 1 Nomination Cycle pursuant to this
Section 5.5(a)(i)(3) will be 5:00 p.m. on the
Day of Gas flow.
(4) The Intraday 2 Nomination Cycle on the Day of
Gas flow shall be as follows:
5:00 p.m. Nomination leaves control of the
nominating party.
5:15 p.m. Receipt of nomination by Transporter
(including from TTTSPs).
5:30 p.m. Transporter sends Quick Response.
8:00 p.m. Receipt of completed confirmations
by Transporter from upstream and
downstream connected parties.
9:00 p.m. Transporter provides scheduled
quantities to Shipper and point
operator.