Reliant Energy Gas Transmission Company
Fifth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/2002, Docket: RP03- 60-000, Status: Effective
Second Revised Sheet No. 296 Second Revised Sheet No. 296 : Effective
Superseding: First Revised Sheet No. 296
GENERAL TERMS AND CONDITIONS
(continued)
5.4 Point(s) of Delivery (continued)
(B) a quantity which is equal to the Contract Demand
less the quantity of total deliveries to Primary
Delivery Points.
(ii) Shippers receiving service under Rate Schedule IT
shall request one or more generally available physical
Delivery Points on Transporter's system as Delivery
Points during the Section 5.5(a) nomination process;
provided that aggregate deliveries shall not exceed
MCQ.
(iii) Shippers receiving wheeling service under Rate
Schedule PHS shall request the Delivery Points
available under such Rate Schedule during the Section
5.5(a) nomination process.
(iv) Shipper (but not a Shipper under Rate Schedule NNTS)
may substitute Primary Delivery Points or otherwise
change MDO's, provided that Contract Demand is not
exceeded. Any increase in or shift of MDO at a
Primary Delivery Point must be in substitution for
relinquished MDO at another Primary Delivery Point.
Deletions, substitutions or additions of Delivery
Points shall be in accordance with the provisions of
Section 10; provided, however, that Transporter will
process and accept or reject, in accordance with such
section,