Northwest Pipeline Corporation
First Revised Volume No. 1-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/02/1991, Docket: RP91-150-000, Status: Effective
Original Sheet No. 417-A Original Sheet No. 417-A : Effective
GENERAL TRANSPORTATION TERMS AND CONDITIONS
(Continued)
12. PRIORITY OF SERVICE (Continued)
12.6 Curtailment Liability. If Transporter is required to curtail
deliveries during the term of the Transportation Agreement and if
curtailment is implemented for any reason, Transporter will not be
liable for any damages caused by implementation of curtailment
procedures as set forth herein except to the extent that such
curtailment is shown to be the result of negligence or misfeasance by
Transporter.
12.7 Transportation Requests. Procedures for requesting transportation
service are set forth in Section 17 below. Each Shipper must complete
a Transportation Request as set forth in Section 17 herein.