East Tennessee Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2000, Docket: RP00-245-000, Status: Effective
Original Sheet No. 111A Original Sheet No. 111A : Superseded
GENERAL TERMS AND CONDITIONS (Continued)
Any modification of an existing service shall be requested by
Shipper/Balancing Party's submission of a request for change via
PASSKEY or by facsimile if necessary. Such request for change,
after having been fully processed and accepted by Transporter,
shall be deemed to have the full force and effect of the
underlying service agreement. Transporter shall maintain a log of
all firm transportation requests.
Upon receipt of such request and after the request has been fully
processed and approved by Transporter, pursuant to the terms and
conditions of the applicable rate schedule and the General Terms
and Conditions of Transporter's FERC Gas Tariff, Transporter shall
approve on-line or by facsimile if necessary, the applicable
Service Agreement, as set forth in Transporter's FERC Gas Tariff
with the agreed upon terms and conditions contained therein.
Shipper shall execute on-line or execute and return via facsimile,
if necessary, the Service Agreement within the time period
specified by the applicable service tariff provision. Except as
provided in Section 7 of the General Terms and Conditions below,
Shippers execution on-line shall consummate a binding contract
between the parties.
5.2 Any request shall include the information listed below.
Shipper/Balancing Party shall provide any additional information
required by Transporter to process the request; provided, that the
request for additional information shall not affect the priority
of Shipper/Balancing Party's request.