Panhandle Eastern Pipe Line Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/25/1996, Docket: RP96-214-000, Status: Effective
First Revised Sheet No. 321F First Revised Sheet No. 321F : Superseded
Superseding: Original Sheet No. 321F
GENERAL TERMS AND CONDITIONS
(Continued)
18.11 Dakota Gasification Transition Cost Surcharge
(a) Applicability
This Section 18.11 establishes the mechanism for the
recovery by Panhandle of certain costs which are
applicable to services provided to Panhandle by ANR
Pipeline Company (ANR), under ANR's Rate Schedule
FTS-1. To recover these Transition Costs, Panhandle
shall be entitled to surcharge Shippers utilizing its
Market Area Storage Facilities under Rate Schedules
WS, PS, FS and IWS to flow through all Dakota
Gasification Costs that Panhandle is required to pay
to ANR.
(b) Definition
As used in this Section 18.11, Dakota Gasification
Transition Costs are those capacity and supply costs
associated with ANR's obligations to Dakota
Gasification Company which the Commission has
permitted ANR to recover from Panhandle pursuant to
Section 28.1(c) of ANR's FERC Gas Tariff, Second
Revised Volume No. 1, or successor tariff.
(c) Filings
(1) The effective date of each Dakota Gasification
Transition Cost Surcharge shall be June 1,
September 1, December 1 and March 1.
(2) Prior to the effective date of each Dakota
Gasification Transition Cost Surcharge, Panhandle
shall file with the Commission and post, as
defined in Section 154.2(d) of the Commission's
Regulations, a statement of the effective Dakota
Gasification Transition Cost Surcharge as
determined in accordance with this Section 18.11.
In each filing, Panhandle shall include
workpapers detailing the basis used to determine
the amount of the surcharge. In the event any
such change is precluded by law from going into
effect on such date, it shall be made effective
as soon thereafter as permitted by law.