Panhandle Eastern Pipe Line Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 05/01/1993, Docket: RS92- 22-005, Status: Effective

Original Sheet No. 309 Original Sheet No. 309 : Superseded







which transmission costs have been allocated; nor

shall it apply to transportation associated with the

withdrawal of contract storage volumes stored on

Panhandle's system (including third-party storage for

which Panhandle has contracted), when the Canadian

Resolution Surcharge is applicable to the

transportation of such gas for injection into



(f)Nature of the Canadian Resolution Surcharges


The Canadian Resolution Surcharges shall be added to

the currently effective rates for all rate schedules

to which such surcharge is or may become applicable.


(g)Billing and Payment of Canadian Resolution Surcharges


Panhandle shall include charges for applicable

Canadian Resolution Surcharges in its regularly

scheduled invoices to affected Shippers to whom the

Canadian Resolution Surcharges are applicable.


(h)Survivability of Canadian Resolution Surcharges


To the extent the period of the effectiveness of the

charges described in Sections 18.6(c) and 18.6(d) has

not expired, the provisions of this Section 18.6

respecting Canadian Resolution Surcharges shall be

fully applicable to successor, replacement and new

rate schedules, other than those described in Section

18.6(e) hereof.