Panhandle Eastern Pipe Line Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2002, Docket: RP00-395-003, Status: Effective
Sixth Revised Sheet No. 279 Sixth Revised Sheet No. 279 : Superseded
Superseding: Fifth Revised Sheet No. 279
GENERAL TERMS AND CONDITIONS
(Continued)
(iii) If the Releasing Shipper specifies a bid
evaluation methodology other than highest rate,
net revenue or present value, or a permanent
release or any other special conditions, the
above timelines shall apply; provided, however,
one additional Business Day will be added to
the evaluation period. Such extended
evaluation period will cause Gas flow to be at
least one day later than Gas could flow under
the timeline set forth in Section 15.4(d)(i)or
Section 15.4(d)(ii).
(e) A party may submit only one bid at a time in response
to a Release Notice. Once a party has submitted a
bid, it may withdraw the bid through the Messenger
system at any time prior to the close of the posting
period specified in Section 15.3(c) without prejudice
to its submitting another bid with an economic value
equal to or greater than the economic value of the
withdrawn bid. If a bid is not withdrawn prior to
the close of the posting period, the bid shall be
binding on the party submitting the bid, subject to
the satisfaction of any contingencies the Releasing
Shipper permits to be satisfied after the close of
the bidding period.
(f) Bids to accept assignment will be posted on the
Messenger system with any contingencies identified
and with the bidder's identity deleted.
15.5 Selection of Replacement Shipper
(a) The Addendum to the Capacity Release Service
Agreement will be issued to the Replacement Shipper
whose bid provides the greatest economic value, as
defined by the Releasing Shipper in accordance with
Section 15.2(b) or, if the Releasing Shipper does not
specify a method of determining economic value, the
economic value will be determined by utilizing the
present value method, and whose bid meets all the
conditions placed upon the assignment by the Releasing
Shipper as provided for in Section 15.2(b), provided
that if the Releasing Shipper has permitted contingent
bids, the selection of a Replacement Shipper may be
delayed in accordance with the contingencies permitted
in the Release Notice. If the bids of two or more
Replacement Shippers provide the same economic value
and both meet all the conditions placed upon the