Panhandle Eastern Pipe Line Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2002, Docket: RP03- 4-000, Status: Effective

Thirteenth Revised Sheet No. 9 Thirteenth Revised Sheet No. 9 : Pending

Superseding: Twelfth Revised Sheet No. 9

CURRENTLY EFFECTIVE RATES

RATE SCHEDULE IOS

IN/OUT STORAGE

 

 

Each rate set forth on this tariff sheet is the currently effective rate pertaining to the

particular rate schedule to which it is referenced, but each such rate is separate and independent

and the change in any such rate shall not thereby effect a change in any other rate schedule.

 

 

Maximum Minimum

Rate Rate Fuel

Description Per Dt. Per Dt. Reimbursement

 

 

Deliverability Charge $ 3.35 1/ - -

 

Capacity Charge 40.28› 1/ - -

 

Injection Charge 0.33 0.33› 1.56%

 

Withdrawal Charge 0.33 0.33 0.53

 

Overrun Charge 14.85 - -

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1/ Maximum rate applicable for capacity release.