Caledonia Gas And Storage

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/30/2010, Docket: RP10-1032-000, Status: Effective

Original Sheet No. 68 Original Sheet No. 68

 

one Gas Day later than under the standard timelines set forth in

Sections 5.5(a) and 5.5(b), above.

(d) Releases Not Subject to Bidding. Prearranged capacity releases of

a duration of thirty-one (31) days or less, to an asset manager (as

defined by FERC regulations at 18 C.F.R. §284.8(h)(3)), or to a

marketer participating in a state-regulated retail access program (as

defined by FERC regulations at 18 C.F.R. § 284.8(h)(4)) are not

required to be posted for bidding pursuant to Section 5.4. Nonetheless,

the Customer may elect to post one of the foregoing releases for

bidding pursuant to Section 5.4, Customer shall notify Caledonia by

providing the information pursuant to Section 5.2, which information

will be posted on the Internet Web Site as required by Section 5.4 in

accordance with the following timelines:

(i) Timely Cycle:

Posting of prearranged deals not subject to bid are due by 10:30 A.M.

CCT.

 

(ii) Evening Cycle:

Posting of prearranged deals not subject to bid are due by 5:00 A.M.

CCT.

 

(iii) Intraday 1 Cycle:

Posting of prearranged deals not subject to bid are due by 9:00 A.M.

CCT.

 

(iv) Intraday 2 Cycle:

Posting of prearranged deals not subject to bid are due by 4:00 P.M.

CCT.

 

(e) Prior to the nomination deadline for the chosen cycle for the begin

date specified in the Customer notice, the Prearranged Customer must

initiate confirmation of prearranged deals electronically. Caledonia

will issue a contract within one hour of notification of the award

posting (with a new contract number, when applicable). Nominations

for Gas flow are possible beginning at the next available nomination

cycle for the effective date of the contract. Such nominations will

be processed in accordance with the nomination and scheduling

requirements of Section 9 of the General Terms and Conditions; however,

in no circumstance will Gas flow prior to the effective date of the

release as specified in Releasing Customer’s offer. If a release of

capacity is exempt from bidding because it is for a term of thirty-one

(31) days or less, a Customer may not roll-over, extend, or in any way

continue the release to the same Customer using the thirty-one (31) day

or less bidding exemption, unless the Customer complies with the

posting and bidding requirements of Section 5.2 or not less