Caledonia Gas And Storage
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/30/2010, Docket: RP10-1032-000, Status: Effective
Original Sheet No. 37 Original Sheet No. 37
schedule and withdraw on an Advanced Interruptible basis quantities of
Gas in excess of Customer’s MDWQ, provided that the quantities
Customer shall have nominated for withdrawal on such Gas Day will not
cause Customer’s Loan Balance to exceed Customer’s MLQ. Such Overrun
Quantities shall be subject to the charge set forth in Section 4.1(e)
of this Rate Schedule.
3.3 Interruptible. Caledonia shall have the right to interrupt or not
to schedule all or part of the Overrun Quantities nominated, subject to
Section 6 of the General Terms and Conditions of this FERC Gas Tariff,
in which event Caledonia shall notify Customer.
4. RATES AND CHARGES
4.1 Rates & Charges. Customer shall pay rates and charges for Advanced
Interruptible Loan Service under this Rate Schedule including the
applicable loan rate components set forth in the AILS Rate Statement
and as described below:
(a) Advanced Interruptible Loan Charge. A charge for each Dth of AILS
available to Customer (Customer’s MLQ). The charge may be on a daily,
monthly, or other basis per agreement between Caledonia and Customer.
(b) Advanced Interruptible Loan Injection Charge. A usage charge for
each Dth of Gas (including fuel, if applicable) injected into
Caledonia’s facilities pursuant to Section 2.1 of this Rate Schedule.
(c) Advanced Interruptible Loan Withdrawal Charge. A usage charge for
each Dth of Gas (including fuel, if applicable) withdrawn from
Caledonia’s facilities pursuant to Section 2.1 of this Rate Schedule.
(d) Overrun Injection Charge. A usage charge for each Dth of Gas
(including fuel, if applicable) injected into Caledonia’s facilities
pursuant to Section 3.1 of this Rate Schedule during a given Month.
(e) Overrun Withdrawal Gas. A usage charge for each Dth of Gas
(including fuel, if applicable) withdrawn from Caledonia’s facilities
pursuant to Section 3.2 of this Rate Schedule during a given Month.
(f) Fuel Reimbursement. The amount of Gas or equivalent charge for fuel
and losses determined in accordance with Section 18 of the General
Terms and Conditions of this FERC Gas Tariff and set forth in
Customer’s AILS Services Agreement.
(g) Regulatory Fees and Charges. Customer shall reimburse Caledonia for
all fees and charges, including, but not limited to, ACA charges, as
required by the Commission or