Caledonia Gas And Storage
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/30/2010, Docket: RP10-1032-000, Status: Effective
Original Sheet No. 27 Original Sheet No. 27
(b) The storage of Gas in amounts up to Customer’s Interruptible MSQ,
provided that all Firm Service obligations have been satisfied; and
(c) The withdrawal from storage on any Gas Day of Customer’s Gas per
Customer’s nomination up to Customer’s MDWQ as stated in the executed
Interruptible Storage Service Agreement with Customer and the Delivery
of such Gas to the Point of Injection/Withdrawal available on
Caledonia’s System, provided that all Firm Service nominations for
withdrawal have been satisfied, and Customer has a quantity of Gas in
Customer’s Interruptible Storage Inventory not less than the quantity
the Customer shall have nominated for withdrawal on such Gas Day.
2.2 Interruptible. Gas which is scheduled for daily injection or
withdrawal under this Rate Schedule is subject to interruption based
upon changes in Firm storage service nominations received by Caledonia
or when necessary to maintain the operational integrity of Caledonia’s
System. Notice of interruption will be given pursuant to Section 6.4 of
the General Terms and Conditions of this FERC Gas Tariff. In the event
that Caledonia notifies the Customer of an interruption in service under
this Rate Schedule, the Customer must cease injections or withdrawals,
in whole or in part, as specified by Caledonia.
2.3 No Capacity Release. Service rights under an ISS Service Agreement
may not be released.
3. OVERRUN SERVICE
3.1 Injection. Provided it can be accomplished by Caledonia without
detriment to Caledonia’s Storage Facility and Caledonia has injection
capacity available, Caledonia may, upon request of Customer and after
confirmation by Customer’s Transporter, schedule and inject on an
Interruptible basis quantities of Gas in excess of Customer’s MDIQ,
provided that Customer’s Interruptible Storage Inventory has not
exceeded Customer’s MSQ. Such Overrun Quantities shall be subject to
the charge set forth in Section 4.1(d) of this Rate Schedule.
3.2 Withdrawal. Provided it can be accomplished by Caledonia without
detriment to Caledonia’s Storage Facility and Caledonia has withdrawal
capacity available, Caledonia may, upon request of Customer and after
confirmation by Customer’s Transporter, schedule and withdraw on an
Interruptible basis quantities of Gas in excess of Customer’s MDWQ,
provided that Customer has a quantity of Gas in Customer’s
Interruptible Storage Inventory not less than the quantities Customer
shall have nominated for withdrawal on such Gas Day. Such Overrun
Quantities shall be subject to the charge set forth in Section 4.1(e)
of this Rate Schedule.