Caledonia Gas And Storage

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/30/2010, Docket: RP10-1032-000, Status: Effective

Original Sheet No. 18 Original Sheet No. 18

 

with Customer and the Delivery of such Gas to the Point of

Injection/Withdrawal available on Caledonia’s System, provided that

Customer has a quantity of Gas in Customer’s Firm Storage Inventory

not less than the quantity Customer shall have nominated for

withdrawal on such Gas Day.

3. OVERRUN SERVICE

3.1 Injection. Provided it can be accomplished by Caledonia without

detriment to Caledonia’s Storage Facility and/or Caledonia’s ability to

meet its Firm obligations to other Customers, Caledonia may, upon

request of Customer and after confirmation by Customer’s Transporter,

schedule and inject on an Interruptible basis quantities of Gas in

excess of Customer’s MDIQ, provided that Customer’s Firm Storage

Inventory has not exceeded Customer’s MSQ. Such Overrun Quantities

shall be subject to the negotiable market-based charge set forth in

Section 4.1(d) of this Rate Schedule.

3.2 Withdrawal. Provided it can be accomplished by Caledonia without

detriment to Caledonia’s Storage Facility and/or Caledonia’s ability to

meet its Firm obligations to other Customers, Caledonia may, upon

request of Customer and after confirmation by Customer’s Transporter,

schedule and withdraw on an Interruptible basis quantities of Gas in

excess of Customer’s MDWQ, provided that Customer has a quantity of Gas

in Customer’s Firm Storage Inventory not less than the quantities

Customer shall have nominated for withdrawal on such Gas Day. Such

Overrun Quantities shall be subject to the negotiable market-based

charge set forth in Section 4.1(e) of this Rate Schedule.

3.3 Interruptible. Caledonia shall have the right to interrupt or not

to schedule all or part of the Overrun Quantities nominated, subject to

Section 6 of the General Terms and Conditions of this FERC Gas Tariff,

in which event Caledonia shall notify Customer.

4. RATES AND CHARGES

4.1 Rates & Charges. The rates and charges paid by Customer for Firm

Storage Service under this Rate Schedule shall include the applicable

storage rate components set forth in the FSS Rate Statement and as

described below:

(a) Storage Reservation Charge. A Monthly charge for each Dth of

Customer’s MSQ.

(b) Storage Injection Charge. A usage charge for each Dth of Customer’s

Gas injected into Caledonia’s facilities pursuant to Section 2.1(a) of

this Rate Schedule during a given Month (including fuel, if applicable).

(c) Storage Withdrawal Charge. A usage charge for each Dth of

Customer’s Gas withdrawn from Caledonia’s facilities