GENERAL TERMS AND CONDITIONS
3.10 Meter. Gas delivered by WTG Hugoton to the Shipper shall be measured by
an adequate meter or meters of standard type, installed, operated and
maintained by WTG Hugoton at its sole expense. In the alternative, the
responsibility for meter installation, operation and/or maintenance may be as
mutually agreed upon between the parties. When more than one meter is used
for measurement of gas delivered to the Shipper, the term "Meter" shall be
construed to mean and include all such meters used for that purpose.
3.11 Receipt and Delivery Point Operator Flow Information Systems. Receipt
and Delivery Point Operators may, subject to WTG Hugoton specifications and at
the operators' sole expense, install flow information systems at WTG Hugoton's
facilities sufficient to provide daily flow information. Such equipment shall
be operated and maintained as agreed to between WTG Hugoton and the Operator.
Receipt and Delivery Point Operators who have installed flow information
systems may provide such information to WTG Hugoton in accordance with the
established parameters, for use in compiling daily imbalances and daily
service charges, subject to reasonable verification. To the extent the
facilities become outdated and are no longer in compliance with WTG Hugoton's
specifications, the Receipt and Delivery Point Operators shall be so notified
by WTG Hugoton, and may install replacement facilities. If the replacement
facilities are not installed within a reasonable period of time, WTG Hugoton
will discontinue accepting data from the outdated facilities and begin using
WTG Hugoton's data.
3.12 Equipment Testing. At reasonable intervals, WTG Hugoton shall test and
adjust to within measurement tolerances all equipment used in making the
determination of factors used under the provision of this Section. Such
equipment shall, at all reasonable times, be subject to test or an inspection
by a representative of the Shipper in the presence of a representative of WTG
Hugoton.
(a) The Shipper shall test, at reasonable intervals, all Shipper
equipment used for measurement of gas where such measurement enters into the
measurement computations and shall at the time of the tests, adjust such
equipment to record accurately. WTG Hugoton's representative shall have the
right to witness such tests, or at reasonable times at WTG Hugoton's election,
to test and inspect such equipment in the presence of the Shipper.