T.W. Phillips Pipeline Corp.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/2010, Docket: RP10-141-001, Status: Effective

First Revised Sheet No. 45 First Revised Sheet No. 45

Superseding: riginal Sheet No. 45

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

8.4. For service required on any day under each of Shipper’s FT or IT Agreements,

Shipper shall provide Transporter with a nomination(s) providing the Shipper’s

requested Receipt Point(s), contract numbers, the applicable service, the quantity

of Gas to be delivered, the requested Delivery Point(s), and such additional

information as Transporter determines to be necessary.

 

8.5. General Rules and Timeline – Pursuant to NAESB Standards 1.3.2, 1.3.3, 1.3.5,

1.3.6, 1.3.20, 1.3.21; the standard nominations timeline shall be as follows:

 

8.5.1. The Timely Nomination Cycle – 11:30 a.m. for nominations leaving control of

the nominating party; 11:45 a.m. for receipt of nominations by Transporter;

noon to send Quick Response; 3:30 p.m. for receipt of completed

confirmations by Transporter from upstream and downstream connected

parties; 4:30 p.m. for receipt of scheduled quantities by Shipper and point

operator (Central Time on the day prior to flow).

 

8.5.2. The Evening Nomination Cycle – 6:00 p.m. for nominations leaving control of

the nominating party; 6:15 p.m. for receipt of nominations by Transporter;

6:30 p.m. to send Quick Response; 9:00 p.m. for receipt of completed

confirmations by Transporter from upstream and downstream connected

parties; 10:00 p.m. for Transporter to provide scheduled quantities to

affected Shippers and point operators, and to provide scheduled quantities

to bumped parties (notice to bumped parties), (Central Time on the day

prior to flow). Scheduled quantities resulting from an Evening Nomination

that does not cause another Service Requester on Transporter to receive

notice that it is being bumped should be effective at 9:00 a.m. on Gas day;

and when an Evening Nomination causes another Service Requester on

Transporter to receive notice that it is being bumped, the scheduled

quantities should be effective at 9:00 a.m. on Gas day.

 

8.5.3. The Intraday 1 Nomination Cycle – 10:00 a.m. for nominations leaving

control of the nominating party; 10:15 a.m. for receipt of nominations by

Transporter; 10:30 a.m. to send Quick Response; 1:00 p.m. for receipt of

completed confirmations by Transporter from upstream and downstream

connected parties; 2:00 p.m. for Transporter to provide scheduled quantities

to affected Shippers and point operators, and to provide scheduled

quantities to bumped parties (notice to bumped parties), (Central Time on

the Gas day). Scheduled quantities resulting from Intraday 1 Nominations

should be effective at 5:00 p.m. on Gas day.