Stingray Pipeline Company, L. L. C.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2008, Docket: RP08-436-000, Status: Effective
First Revised Sheet No. 79 First Revised Sheet No. 79
Superseding: Original Revised Sheet No. 79
RATE SCHEDULE FTS-2
FIRM TRANSPORTATION SERVICE
receipts and actual deliveries shall be eliminated by cash-
out on a monthly basis in accordance with the General Terms
and Conditions of this Tariff. In the event that Stingray,
on any Day, is unable to receive and/or deliver the total
nominations of all Shippers under any Rate Schedule of this
Tariff, Stingray shall limit receipts and/or deliveries of
Gas in accordance with Section 3 of the General Terms and
Conditions of this Tariff.
17. RECEIPTS AND DELIVERY AND UPSTREAM AND DOWNSTREAM ARRANGEMANTS
17.1 The Firm Receipt Points for Gas tendered to Stingray for
transportation hereunder and the Firm Delivery Point(s) for
Gas delivered by Stingray to Shipper (or to a third party on
behalf of Shipper) hereunder shall be specified in the FTS-2
Agreement. For each individual Firm Receipt and Delivery
Point, and for the aggregate of all such points, Stingray's
maximum obligation to accept and deliver Gas on a firm basis
shall be specified in Dth in the FTS-2 Agreement. The sum
of the MDQs for Firm Receipt Points and the sum of the MDQs
for Firm Delivery Points shall not exceed the aggregate MDQ.
Shipper may utilize any and all points as Interruptible
Receipt or Delivery Points as specified in the General Terms
and Conditions of this Tariff.
17.2 Conditions of delivery at Receipt and Delivery Points are
set out in the General Terms and Conditions of this Tariff.
17.3 Shipper shall make all necessary arrangements with other
parties: (1) at or upstream of the Receipt Point(s) where
Gas is tendered to Stingray hereunder; and (2) at or
downstream of the Delivery Point(s) where Stingray delivers
Gas hereunder to or for the account of Shipper. Such
arrangements must be consistent with this Rate Schedule FTS-
2 and must be coordinated with Stingray Receipt and Delivery
Point in accordance with the General Terms and Conditions of
this Tariff. It shall be Shipper's responsibility to cause
Gas to be delivered to Stingray at Receipt Point(s), and to
cause Gas to be taken from Stingray at Delivery Point(s), in
accordance with the information supplied to Stingray.