Stingray Pipeline Company, L. L. C.

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2008, Docket: RP08-436-000, Status: Effective

First Revised Sheet No. 78 First Revised Sheet No. 78

Superseding: Original Revised Sheet No. 78

 

RATE SCHEDULE FTS-2

FIRM TRANSPORTATION SERVICE

 

projected date when such new reserves will commence to be produced

from transportation through Stingray's Pipeline Facilities, and

the expected duration of such transportation. All such

information provided to Stingray pursuant to this Section shall be

kept confidential by Stingray.

 

14. RELEASE OF FIRM CAPACITY

 

Any Shipper receiving service under this Rate Schedule FTS-2 shall

have the right to release its firm capacity rights on a temporary

basis only and in accordance with Section 16 of the General Terms

and Conditions of this Tariff.

 

15. TERM

 

15.1 The term of service hereunder shall be set forth in the FTS-

2 Agreement between Shipper and Stingray.

 

15.2 Stingray may terminate any FTS-2 Agreement if Stingray is

required by the FERC or some other agency or court to

provide firm service for others utilizing the System

capacity or capability required for service under such FTS-2

Agreement or if Stingray ceases (after receipt of any

requisite regulatory authorization) to offer service of the

type covered by the FTS-2 Agreement. Stingray's ability to

terminate any FTS-2 Agreement under this provision is

intended to ensure that the contract term does not extend

beyond the regulatory authority to provide the service and

that the contract is consistent with the regulatory

authority to provide the service.

 

16. NOMINATIONS, SCHEDULING CHARGES AND IMBALANCES

 

16.1 Shipper shall provide Stingray with daily nominations of

receipts and deliveries by Receipt and Delivery Point in

accordance with the General Terms and Conditions of this

Tariff. It shall be Shipper's responsibility to cause Gas

to be delivered to Stingray at Receipt Point(s), and to

cause Gas to be taken from Stingray at Delivery Point(s), in

accordance with the information supplied to Stingray.

 

16.2 It shall be Shipper's responsibility to keep receipts and

deliveries in balance. Stingray may curtail service

hereunder to the extent necessary to bring receipts and

deliveries into balance. Any imbalance between actual