Stingray Pipeline Company, L. L. C.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2008, Docket: RP08-436-000, Status: Effective
Fifth Revised Sheet No. 62 Fifth Revised Sheet No. 62
Superseding: Fourth Revised Sheet No. 62
RATE SCHEDULE FTS-2
FIRM TRANSPORTATION SERVICE
(b) Stingray shall promptly notify Shipper if it cannot
satisfy an otherwise valid request, in whole or in
part, due to lack of capacity or System capability or
if the request is incomplete or does not comply with
this Rate Schedule FTS-2.
(1) Any request shall be null and void unless it is
substantially complete and complies with this
Rate Schedule FTS-2. In the event a request is
substantially but not entirely complete,
Stingray shall inform Shipper in writing of the
specific items needed to complete the FTS-2
Agreement, after which Shipper shall have
fifteen (15) Days to provide the specified
information. In the event such information is
not received within fifteen (15) Days, Shipper's
request shall be null and void.
(2) If Stingray cannot satisfy a request due to
insufficient System capacity or capability, such
request shall be of a continuing nature and
shall remain valid unless and until Shipper
notifies Stingray that it desires to withdraw
its request except as follows: Stingray may at
any time tender an FTS-2 Agreement to Shipper
consistent with Shipper's request which is
conditional on the future availability of System
capacity and capability. Such conditional
agreement must allow Shipper to void the
contract and withdraw its request if Shipper's
notice of withdrawal is given prior to Shipper
receiving notice from Stingray that System
capacity and capability is available and the
request is approved. If Shipper declines to
execute such an agreement within thirty (30)
Days, its request shall be null and void.
(c) Stingray shall tender an FTS-2 Agreement to Shipper
for execution when Shipper's request for service is
accepted. Unless waived by Stingray, a request for
service shall be invalid if Shipper fails to execute
an FTS-2 Agreement hereunder within thirty (30) Days
after an FTS-2 Agreement has been tendered by Stingray
for execution.