Empire Pipeline, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/10/2008, Docket: CP06-5-010, Status: Effective
Original Sheet No. 22 Original Sheet No. 22
RATE SCHEDULE FT
Firm Transportation Service
(Continued)
3. RATES (Cont'd.)
3.6 If Transporter fails to tender Gas for redelivery at the Point(s)
of Delivery for the account of a Shipper during any Day, due to
the Transporter's scheduling of necessary maintenance and repair
of pipeline facilities, necessary maintenance and repair of
compression facilities, and/or facility outages for tie-in of new
facilities, but not including any incidence of force majeure, as
defined in Section 28.6 of the General Terms and Conditions, the
quantity of Gas that Shipper has nominated for, or makes available
to Transporter on, such Day, or Shipper's Maximum Daily Quantity,
whichever is less, then subject to the provisions of the General
Terms and Conditions, the Shipper shall be entitled to a
reservation charge credit equal to the Reservation Charge
multiplied by twelve (Months) and divided by 365 (Days), then
multiplied by the excess of (a) such quantity of Gas nominated or
made available for delivery by Shipper, whichever is less, over
(b) the Maximum Daily Quantity, or the quantity actually received
by Transporter for the account of Shipper during such Day,
whichever is less. This Section 3.6 shall not apply to a
negotiated rate agreement unless such agreement specifically
provides that this section shall apply or unless service was
provided under such agreement prior to the effective date of this
FERC Gas tariff.
3.7 If Transporter fails to tender Gas for redelivery at the Point(s)
of Delivery for the account of a Shipper during any Day, due to
the incidence of force majeure, as defined in Section 28.6 of the
General Terms and Conditions, the quantity of Gas that Shipper has
nominated for, or makes available to Transporter on, such Day, or
Shipper's Maximum Daily Quantity, whichever is less, then subject
to the provisions of the General Terms and Conditions, the Shipper
shall be entitled to a reservation charge credit equal to the
applicable percentage of the Reservation Charge shown on Sheet No.
6 multiplied by twelve (Months) and divided by 365 (Days), then
multiplied by the excess of (a) such quantity of Gas nominated or
made available for delivery by Shipper, whichever is less,