RATE SCHEDULE FT
Firm Transportation Service
(Continued)
2. APPLICABILITY AND CHARACTER OF SERVICE (Cont'd.)
(c) to take delivery of quantities of gas at any firm primary Point
of Delivery in excess of the MDQ specified in the FT Service
Agreement for that Point of Delivery, nor
(d) to take delivery of quantities of gas in excess of the Contract
MDQ on any day at any combination of Point(s) of Delivery.
The Contract MDQ shall be the sum of the MDQ's applicable to each
primary Point of Delivery. The sum of the MDQ's applicable to each
primary Point of Receipt shall also equal the Contract MDQ.
2.4 Subject to the provisions of this Rate Schedule FT, Transporter
will:
(a) accept natural gas tendered by Shipper at a secondary Point of
Receipt, and
(b) deliver natural gas for the Shipper's account at a secondary
Point of Delivery;
provided that such acceptance or delivery would not impair
Transporter's ability to provide firm transportation (to another
Shipper from a firm primary Point of Receipt or firm primary Point
of Delivery) and provided further that any such Point(s) of
Delivery are equipped with measurement, control and communication
equipment required for firm Point(s) of Delivery. Use of secondary
Point(s) of Receipt or Point(s) of Delivery by FT Shippers shall be
superior to the use of such points by interruptible shippers.
Unless specifically provided otherwise in a written amendment to
the FT Service Agreement under Section 3.2 hereof or a Negotiated
Rate Agreement under Section 18.2 of the General Terms and
Conditions, Transporter's maximum rates shall apply to
transportation involving the use of secondary Point(s) of Receipt