13.2 Pipeline may designate a paper pooling point ("Pool") on Pipeline's

system for every Pooling Service Agreement executed pursuant to this

Section. The Pool is not a physical point on Pipeline's system, but

is to be used solely for nomination and scheduling purposes in order

to allow Shipper to aggregate gas supplies from multiple Receipt

Points to a single virtual point ("Aggregation Nomination") and to

disaggregate gas supply from a pool to multiple Delivery Points

("Disaggregation Nomination") on Pipeline's system. A Shipper will

nominate gas volumes from one or more Receipt Points to the Pool

utilizing its Pooling Service Agreement in order to aggregate

supplies. A Shipper may utilize any number of Service Agreements or

Capacity Release Agreements to transport gas out of the Pool. A

Shipper must nominate all gas volumes in a Pool to the Delivery

Point(s) on the same Gas Day.

 

13.3 Nominations to and from the Pool will be subject to the same

nomination and confirmation procedures as all other receipts and

deliveries on Pipeline's System, as more particularly described in

GT&Cs Section 5.4.

 

13.4 For purposes of allocating volumes to the Pooling Service Agreement,

all Aggregation Nominations will be considered received by the Pool.

Total daily quantities of gas delivered to the Pool under the

Aggregation Nomination must equal the total daily quantity of gas

nominated on the Disaggregation Nomination at the Pool for each

Pooling Service Agreement.

 

13.5 Pipeline shall have the right to balance any discrepancy between the

sum of the Aggregation Nominations for a Gas Day and the sum of the

Disaggregation Nominations for that Gas Day, and to apply overrun

charges, as set forth in GT&Cs Section 7.

 

13.6 Pipeline will balance any discrepancy between the sum of the

Aggregation Nominations for a Gas Day and the sum of the

Disaggregation Nominations for that Gas Day prior to conclusion of

the final nomination cycle by adjusting the scheduled deliveries of

the Aggregation Nomination and Disaggregation Nominations as

appropriate. Pipeline shall use Shipper's schedule ranks on the

Aggregation Nominations to make said adjustments.