Cameron Interstate Pipeline, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2008, Docket: RP08-647-000, Status: Effective
Original Sheet No. 86 Original Sheet No. 86
GENERAL TERMS AND CONDITIONS
(continued)
operator on a pro-rata basis until the total allocated
quantity is equal to the total measured quantity. If
necessary, Pipeline shall reduce all remaining
deliveries at the Delivery Point(s) where Pipeline
tenders gas to the Delivery Point operator on a pro-rata
basis until the allocated quantity is equal to the
measured quantity.
Prior-period adjustments to scheduled quantities and
PDAs shall be permitted by Pipeline only if all parties
affected by the resulting prior period reallocation
(including Pipeline) consent in writing to the
adjustment; provided, however, Pipeline shall not
unreasonably withhold such consent.
(b) Deliveries at Interconnects
An imbalance for an OBA Party shall be based on the
difference between total actual quantities of gas
received or delivered through the affected meter and the
total aggregated scheduled quantities for that meter,
which shall be used as the actual quantities of gas
received or delivered. Imbalances will be resolved
pursuant to the OBA between Pipeline and the OBA Party.
7.4 Determination of Make-Up Receipts and Deliveries.
Make-up quantities, including imbalance quantities that are being
resolved in-kind, shall be deemed to be the "last through the
meter." Imbalance quantities returned in-kind in the current Month
are applied first to the previous Month imbalance until such balance
is zero and then applied to the current Month imbalance.