GENERAL TERMS AND CONDITIONS
8. ELECTRONIC BULLETIN BOARD (Cont'd)
8.4 (f) The price, term, quantity and names of parties requesting an
assignment of transportation service pursuant to Section 18
of the General Terms and Conditions.
(g) Riverside's currently effective FERC Gas Tariff's General
Terms and Conditions.
(h) On a best efforts basis, information concerning operational
pressures at major pipeline interconnection points.
(i) Information concerning Shipper imbalances available for
trading pursuant to Section 15.2 of the General Terms and
Conditions.
8.5 Any provisions of this FERC Gas Tariff requiring that matters be
written or in writing shall be satisfied by either Shipper or
Riverside utilizing electronic transmission through the EBB System
(once operational) in accordance with the procedures for
utilization of the EBB System, provided, however, that
notifications utilizing the EBB System which require actions by
Shipper or Riverside within 48 hours or less shall also be
communicated by telephone, facsimile, or in writing. All other
provisions requiring items or information to be written or in
writing remain unchanged.
9. FORCE MAJEURE
9.1 In the event either party hereto is rendered unable, wholly or in
part by force majeure to carry out its obligations under this
contract other than to make payments due hereunder, the
obligations of the party so far as they are affected by such force
majeure shall be suspended during the continuance of any inability
so caused, but for no longer period, and such cause shall as far
as possible be remedied with all reasonable dispatch.