Ngo Transmission, Inc.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/22/2003, Docket: RP04- 67-000, Status: Effective
Original Sheet No. 34 Original Sheet No. 34 : Effective
6.2 New Facilities:
(a) In addition to the charges pursuant to Section 5.1 of this
Rate Schedule, if Transporter agrees to construct facilities
for service requested by Shipper, Transporter shall charge
Shipper an advance equal in amount to 100% of the estimated
costs (including a gross-up for the income tax effects or
reimbursement) of facilities constructed at the Shipper's
request in order to provide transportation and/or storage
service under this Rate Schedule. Further, Transporter
shall charge Shipper an advance equal in amount to 100% of
the estimated costs (including a gross-up for the income tax
effects of reimbursement) to be incurred by Transporter for
appurtenant facilities and equipment, including but not
limited to electronic custody transfer equipment, metering
facilities, gradiometers, calorimeters, flow controllers or
other measurement or metering facilities. Such estimated
advance payments shall be subject to true-up to actual costs
incurred by Transporter for the construction of
transportation and/or storage and appurtenant facilities
within 30 days following completion of construction of such
facilities.
(b) Alternatively, if Transporter and Shipper mutually agree,
the costs of such facilities as determined pursuant to
Section 6.2(a) of this Rate Schedule may be recovered
through an additional monthly charge over an agreed period.
6.3 Incidental Charges: In addition to the charges pursuant to
Sections 6.1 and 6.2 of this Rate Schedule, Transporter may charge
Shipper an amount to reimburse Transporter 100% for any filing or
similar fees, and if applicable, sales or use tax that have not
been previously paid by Shipper, which Transporter incurs in
establishing or rendering service. Shipper shall also pay
Transporter any applicable penalties or charges specified in the
General Terms and Conditions of this Tariff.
6.4 Retainage: Transporter shall deduct from the volume tendered to
Transporter by Shipper, an amount of gas sufficient to compensate
Transporter for compressor station fuel, line loss and/or other
utility purposes, plus other unaccounted for gas used in the
operation of Transporter's pipeline system in connection with such
transportation. The applicable retain age percentage shall be
stated in the effective Notice of Rates in this Tariff.