Monroe Gas Storage Company, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/21/2010, Docket: RP09-447-004, Status: Effective
First Revised Sheet No. 125 First Revised Sheet No. 125
Superseding: Original Sheet No. 125
GENERAL TERMS AND CONDITIONS
(Continued)
2. CONTRACTING FOR STORAGE SERVICE (Continued)
2.8 Priority of Service (Continued)
(c) Should two or more Interruptible Customers have the same
priority, capacity will be allocated to each Customer on a pro
rata basis.
2.9 As part of the original Service Agreement or thereafter at any time
prior to the expiration of the term of a Service Agreement and prior to
Operator’s posting the availability of capacity under Operator’s right
of first refusal provisions, if applicable, Operator and Customer may
mutually agree to an option to extend or an extension of the term of
the Service Agreement. The length of time of any such extension will be
negotiated on a case-by-case basis, in a not unduly discriminatory
manner.
2.10 Operator shall not be required to perform the requested service in the
event all facilities necessary to render the requested service do not
exist at the time the request for service is submitted to Operator.
2.11 No request for Service from a Point of Receipt or to a Point of
Delivery shall be granted if to do so would impair Operator’s ability
to render Services pursuant to Operator’s Rate Schedule FSS of this
FERC Gas Tariff.
2.12 Operator shall not be required to provide any requested Service under
any Rate Schedule which would require construction or acquisition by
Operator of new facilities or expansion of existing facilities.