West Texas Gas, Inc.
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/1996, Docket: RP96-377-000, Status: Effective
Original Sheet No. 32R Original Sheet No. 32R : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
19.6 Assessment of past performance (Continued):
(c) Gas costs requiring specific approval for surcharge
recovery. The amount of gas cost which requires specific ap-
proval by the Commission for surcharge recovery is the difference
obtained by subtracting Y from X, if greater than zero, where:
X= The actual cost of gas purchased in a test interval
determined in paragraph (d) of this section; and
Y= The test amount determined by multiplying the computed
projected gas costs, determined in Paragraph 19.6(e),
by 1.03.
(d) Actual cost of gas purchased. The actual cost of gas
purchased is the monthly amounts determined in Paragraph
19.5(g)(1) hereof for the gas purchased in the test interval:
(1) Less adjustments for exchange transactions and
transportation imbalances;
(2) Including only the gas cost components that were used
to compute the projected average cost of gas that is
compared in a test interval; and
(3) Excluding any demand costs permitted to be passed
through a pipeline's two-part rates on an as-billed basis
under Paragraph 19.5(b)(2).
(e) Computed projected cost of gas. Seller shall
calculate its computed projected gas costs by multiplying:
(1) The quantities of natural gas purchased and/or received
during a PGA effective period within a test interval by