(a) Daily Scheduling Charges - If on any day
Shipper delivers to Norte¤o at the Receipt
Point(s) quantities which are in excess of
("Excess Deliveries") or deficient by
("Deficient Deliveries") the greater of 50
MMBTU or 10 percent of the transportation
quantities scheduled by Norte¤o, Shipper
shall have forty eight hours after
notification by Norte¤o, or such other period
of time as reasonably required by Norte¤o to
protect the integrity of its system, to
initiate corrective action at the affected
Receipt Point(s) and Delivery Point(s). In
the event Shipper fails to initiate the
corrective action mutually agreed upon by
Shipper and Norte¤o's gas dispatchers within
the period agreed upon, Norte¤o shall charge
Shipper a Daily Scheduling charge of $0.10
per day per MMBTU of Excess Deliveries or
Deficient Deliveries, for each day as long as
the Excess Deliveries or Deficient Deliveries
exist, until Shipper brings its cumulative
imbalance within the 10 percent tolerance.
(b) Daily Balancing Charges - If on any day
Shipper delivers to Norte¤o at the Receipt
Point(s) quantities which are in excess of
("Positive Imbalance") or deficient by
("Negative Imbalance")the greater of 50 MMBTU
or 10 percent of the transportation
quantities taken by Shipper at the Delivery
Points, Shipper shall have forty eight hours
after notification by Norte¤o, or such other
period of time as reasonably required by
Norte¤o to protect the integrity of its
system, to initiate corrective action
mutually agreed upon by Shipper's and
Norte¤o's gas dispatchers, at each affected
Receipt Point and Delivery Point. In the
event Shipper fails to initiate the
corrective action mutually agreed upon by
Shipper's and Norte¤o's gas dispatchers
within the period agreed upon, Norte¤o shall
charge Shipper a Daily Imbalance Charge of
$0.10 per day per MMBTU of Positive Imbalance
or Negative Imbalance, for each day as long