GENERAL TERMS AND CONDITIONS
(continued)
definitely or agreed upon. If the period is not
known or agreed upon, the correction shall be made
for a period of one-half of the time elapsed since
the last test but shall not exceed sixteen (16)
days.
6.2 Failure of Meters - In the event a meter is out of
service or registering inaccurately, the volume of
gas delivered shall be determined:
(a) By using the registration of any check meter
or meters, if installed and accurately
registering; or, in the absence of (a)
(b) By correcting the error if the percentage of
error is ascertainable by calibration, tests,
or mathematical calculations; or in the
absence of both (a) and (b), then
(c) By estimating the quantity of delivery during
a period under similar conditions when the
meter was registering accurately.
7. QUALITY:
7.1 The provisions set forth in this Section 7.1,
shall apply to all gas delivered by Norte¤o under
this Tariff.
(a) Heat Content - The natural gas shall have a
Heat Content of not less than nine hundred
and fifty (950) BTUs per cubic foot.
(b) Freedom from Objectionable Matter - The
natural gas delivered by Norte¤o under this
Tariff shall be commercially free (at
prevailing pressure and temperature in
Norte¤o's pipeline) from dust, or other solid
or liquid matters which might interfere with
its merchantability or cause injury to or
interference with proper operation of the
lines, regulators, meters or other facilities
through which it flows; and shall not contain
more than twenty grains of total sulphur nor
more than one grain of hydrogen sulphide per