Original Sheet No. 90C Original Sheet No. 90C TRANSPORTATION GENERAL TERMS AND CONDITIONS (Continued) 24. POLICY FOR CONSTRUCTION OF NEW RECEIPT OR DELIVERY FACILITIES All requests for new interconnects must be made in writing. UnlessTransporter agrees otherwise, the party requesting the new interconnect shallreimburse MIGC or cause MIGC to be reimbursed for any and all reasonablecosts and expenses incurred in constructing, establishing or modifying thefacilities required to establish a new interconnection on existing facilitiesfor receipt or delivery of Gas hereunder. Any agreement by Transporter to bearall or a portion of new interconnect costs shall be done because suchconstruction is economically or operationally beneficial to Transporter andShippers, shall be done in a not unduly discriminatory manner and shall beexercised in Transporter's reasonable discretion. In this regard, all newreceipt and delivery meters shall require EGM which shall be owned by MIGC andall new delivery meters shall require a Flow Control Device with pressureoverride features that can be remotely operated by MIGC. MIGC also must be thecustody transfer party at the proposed facility. In addition to the above requirements, MIGC will agree to construct anew interconnect or modify an existing interconnect on the following terms: (1) The construction of the new interconnect will not create anysignificant operational problems for MIGC; (2) The proposed interconnect will not adversely affect the rendi-tion of existing service or adversely alter the operation of the pipelinesystem; (3) The new interconnect must be at a mutually agreeable locationon the MIGC system; provided, however, that MIGC may not deny a customer'srequest for specific placement of the interconnect without adequateoperational, environmental, or legal justification; (4) In order to properly and prudently design and size the newinterconnect, MIGC must be provided with reasonable and reliable dataconcerning the interconnecting facilities, including the delivery pressures,and anticipated hourly, daily, monthly and annual volume levels of the servicethat supports the new interconnect and such other data as is reasonablyrequired to construct the interconnect facility;