Bobcat Gas Storage

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/15/2008, Docket: RP08-608-000, Status: Effective

Original Sheet No. 89 Original Sheet No. 89

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

7. NOMINATIONS AND SCHEDULING (Continued)

 

7.2 Bobcat will accept nominations for service as follows: (Continued)

 

(f) Minimum NAESB Nomination Standards (Continued)

 

(2) The Evening Nomination Cycle: 6:00 p.m. for

nominations leaving control of the nominating party;

6:15 p.m. for receipt of nominations by Bobcat

(including from TTTSPs); 6:30 p.m. to send Quick

Response; 9:00 p.m. for receipt of completed

confirmations by Bobcat from upstream and downstream

connected parties; 10:00 p.m. for Bobcat to provide

scheduled quantities to affected Customers and point

operators, and to provide scheduled quantities to

bumped parties (notice to bumped parties) (Central

Clock Time on the Day prior to flow). Scheduled

quantities resulting from an Evening Nomination should

be effective at 9:00 a.m. on the Day.

 

(3) The Intraday 1 Nomination Cycle: 10:00 a.m. for

nominations leaving control of the nominating party;

10:15 a.m. for receipt of nominations by Bobcat

(including from TTTSPs); 10:30 a.m. to send Quick

Response; 1:00 p.m. for receipt of completed

confirmations by Bobcat from upstream and downstream

connected parties; 2:00 p.m. for Bobcat to provide

scheduled quantities to affected Customers and point

operators, and to provide scheduled quantities to

bumped parties (notice to bumped parties),(Central

Clock Time on the Day). Scheduled quantities

resulting from Intraday 1 Nominations should be

effective at 5:00 p.m. on the Day.