Steckman Ridge, LP

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2009, Docket: RP09-389-000, Status: Effective

Original Sheet No. 258 Original Sheet No. 258

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

10. NOMINATIONS (continued)

 

10.2 Nomination Timeline. (continued)

 

(3) The Intraday 1 Nomination Cycle: 10:00 a.m. for

nominations leaving control of the nominating party;

10:15 a.m. for receipt of nominations by Steckman

Ridge (including from TTTSPs); 10:30 a.m. to send

Quick Response; 1:00 p.m. for receipt of completed

confirmations by Steckman Ridge from upstream and

downstream connected parties; 2:00 p.m. for Steckman

Ridge to provide scheduled quantities to affected

Customers and point operators, and to provide

scheduled quantities to bumped parties (notice to

bumped parties), (central clock time on the Gas Day).

Scheduled quantities resulting from Intraday 1

Nominations shall be effective at 5:00 p.m. on the Gas

Day.

 

(4) The Intraday 2 Nomination Cycle: 5:00 p.m. for

nominations leaving control of the nominating party;

5:15 p.m. for receipt of nominations by Steckman Ridge

(including from TTTSPs); 5:30 p.m. to send Quick

Response; 8:00 p.m. for receipt of completed

confirmations by Steckman Ridge from upstream and

downstream connected parties; 9:00 p.m. for Steckman

Ridge to provide scheduled quantities to affected

Customers and point operators (central clock time on

the Gas Day). Scheduled quantities resulting from

Intraday 2 Nominations shall be effective at 9:00 p.m.

on the Gas Day. Bumping is not allowed during the

Intraday 2 Nomination Cycle.

 

For the purposes of subsections (2), (3) and (4) above, the

term "provide" shall mean, for transmittals pursuant to

NAESB WGQ standards 1.4.x, receipt at the designated site,

and for purposes of other forms of transmittal, it shall

mean send or post.

 

The sending party shall adhere to the nomination,

confirmation and scheduling deadlines. It is the party

receiving the request who has the right to waive the

deadline.

 

10.3 Customer shall make available and tender any Gas to be injected

hereunder and receive and accept delivery, upon tender by Steckman

Ridge, of any Gas requested to be withdrawn from storage. The

quantity of Gas Stored for the account of Customer shall be

increased or decreased upon injection into or withdrawal of Gas

from storage, as applicable. Customer shall not (unless otherwise

agreed by Steckman Ridge) receive or deliver Gas, nor shall

Steckman Ridge be obligated to receive or deliver Gas on an hourly

basis at rates of flow in excess of 1/24 of Customer's MDIQ, MDRO,

MDWQ or MDDO. As determined by Steckman Ridge in its non-

discriminatory and reasonable judgment, hourly flow rates above

1/24 of Customer's MDRO or MDDO may be permitted; such flow rates

shall be referred to as Accelerated Injections and Accelerated

Withdrawals, respectively.