Cimarron River Pipeline, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2008, Docket: CP08-17-001, Status: Effective
Original Sheet No. 321 Original Sheet No. 321
GENERAL TERMS AND CONDITIONS
21. REQUESTS FOR ADDITIONAL FACILITIES
21.1 Requirements: Transporter will agree to construct a new
interconnect or modify an existing interconnect on the following terms:
(i) All requests for new interconnects or facility
modifications must be made in writing.
(ii) Unless mutually agreed upon on a not unduly discriminatory
basis, the party requesting the new interconnect or facility modification
shall reimburse Transporter or cause Transporter to be reimbursed for
reasonable costs and expenses incurred in planning, designing, constructing,
establishing or modifying the facilities required to establish a new
interconnection on existing facilities for receipt or delivery of gas.
Alternatively, the party requesting the interconnect may perform the
construction at its own cost in compliance with Transporter's technical
requirements.
(iii) All new receipt and delivery meters shall require
electronic gas measurement with radio telemetry, or EGM, which shall be owned
by Transporter. All new delivery meters shall require EGM, and if requested
by Transporter, a flow control device with pressure override features that
can be operated remotely by Transporter. Transporter also must be the
custody transfer party at the proposed facility.
(iv) The construction or operation of the new interconnect or
modified facility will not create any significant operational problems for
Transporter.
(v) The proposed interconnect or facility modification will not
adversely affect the rendition of existing service or adversely alter the
operation of the pipeline system, including the dilution of the gas stream
(Btu or GPM content).
(vi) The new interconnect must be at a mutually agreeable
location on Transporter's system; provided that Transporter may not deny a
customer's request for specific placement of the interconnect without
adequate operational, environmental, or legal justification.
(vii) To design and size the new interconnect or modification
properly and prudently, Transporter must receive reasonable and reliable data
concerning the interconnecting facilities, including pressures, and
anticipated hourly, daily, monthly, and annual volume levels of the service
that supports the new interconnect and other data as reasonably required to
design and construct the interconnect facility.