1. DEFINITIONS
The following terms shall have the following meanings when used in this
Tariff, these General Terms and Conditions, or in a Transportation Service
Agreement ("TSA") or MID Pooling Service Agreement ("MPS Agreement") signed
for service under a Rate Schedule contained in this Tariff, whether or not
used with initial capitals:
(a) "Annual" - the consecutive 12 months January through December.
(b) "British Thermal Unit" or "Btu" - a measurement unit for a quantity of
energy available or released as heat.
(c) "Business Day" - Monday through Friday, excluding federal banking
holidays for transactions in the U.S., and similar holidays for
transactions occurring in Canada and Mexico.
(d) "Central clock time" or "CCT" - central daylight time when daylight
savings time is in effect and central standard time when daylight
savings time is not in effect.
(e) "Day" or "day" - a period of twenty four consecutive hours, beginning
and ending at 9:00 a.m. CCT.
(f) "Dekatherm" or "Dth" - the quantity of heat energy equivalent to
1,000,000 British Thermal Units, or one MMBtu. One Dekatherm of gas
means the quantity of gas that contains one Dekatherm of heat energy.
(g) "Delivery Point" - the point, which may or may not be a physical point,
at which Transporter delivers gas to the Shipper.
(h) "Delivery Point Operator" - Any person interconnected to Transporter or
acting as agent for the interconnected party who is authorized to
confirm Shipper Delivery Point nominations and ensure, in cooperation
with the Shipper and other parties in the confirmation path, that
physical flows conform to the Delivery Point nominations. The Delivery
Point Operator must have the ability to control or cause control of the
physical operation of the facilities interconnected to Transporter's
receipt facilities.
(i) "Evaluation Period" - the period between Transporter's receipt of
Shipper's valid request for firm transportation service and Shipper's
execution of a FT TSA.
(j) "FERC" or "Commission" - the Federal Energy Regulatory Commission and
any successor regulatory body.