Kinder Morgan Louisiana Pipeline LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/01/2009, Docket: RP09-257-000, Status: Effective

Original Sheet No. 137 Original Sheet No. 137

 

GENERAL TERMS AND CONDITIONS

----------------------------

 

6.4 CONFIRMATION BY KMLP

 

(a) Nominations made in accordance with Sections 6.2,

6.3, and 6.5 hereof shall not become effective until KMLP has

confirmed the nominated receipts and deliveries with upstream and

downstream parties, subject to Section 6.5(c). Shipper shall designate

the appropriate person(s) who has the authority to resolve allocation

issues, if requested by KMLP and, if requested by KMLP, the

appropriate person(s) to confirm nominations. Confirmations must be

submitted to KMLP through its Interactive Website, or such other

electronic means as are mutually agreed upon by KMLP and Shipper.

 

(b) Subject to Section 6.2 and the other provisions of

this Tariff, KMLP shall provide Shippers and point operators via its

Interactive Website, or by EDI, the quantities that have been

scheduled to flow for that Shipper and point operator on the next Day.

 

(c) Unless otherwise provided in an Operational Flow

Order, default confirmation procedures are as follows:

 

(i) With respect to the timely nomination/

confirmation process at a Receipt or Delivery Point, in the absence of

agreement to the contrary, the lesser of the confirmation quantities

will be the confirmed quantity. If there is no response to a Request

For Confirmation or an unsolicited Confirmation Response, the lesser

the confirmation quantity or the previously scheduled quantity will be

the new confirmed quantity.

 

(ii) With respect to the processing of requests for

increases during the Intra-Day nomination/confirmation process, in the

absence of agreement to the contrary, the lesser of the confirmation

quantities will be the new confirmed quantity. If there is no

response to a Request For Confirmation or an unsolicited Confirmation

Response, the previously scheduled quantity will be the new confirmed

quantity.