MidContinent Express Pipeline LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/01/2009, Docket: RP09-798-000, Status: Effective

First Revised Sheet No. 113 First Revised Sheet No. 113

Superseding: Original Sheet No. 113

 

GENERAL TERMS AND CONDITIONS

----------------------------

 

1.45 UNDERAGE AVERAGE MONTHLY INDEX PRICE (UAMIP)

 

The Underage Average Monthly Index Price or "UAMIP"

shall mean the index price used in determining cashout amounts for

underages as provided in Section 10.4 of these General Terms and

Conditions.

 

1.46 YEAR

 

"Year" shall mean a period of three hundred sixty-five

(365) consecutive days or three hundred sixty-six (366) consecutive

days if such period includes February 29.

 

1.47 ZONE 1

 

"Zone 1" shall mean that portion of the System which

extends from the beginning of the System in Bryan County, Oklahoma,

to the interconnection with the facilities of Columbia Gulf

Transmission Corporation near Perryville, Louisiana. The Leased

Capacity is not included in either Zone 1 or Zone 2.

 

1.48 ZONE 2

 

"Zone 2" shall mean that part of the System which

extends from the terminus of Zone 1 to an interconnection with the

facilities of Transcontinental Gas Pipe Line Corporation in Choctaw

County, Alabama.

 

1.49 ZONE BOUNDARY TRANSFER POINT

 

"Zone Boundary Transfer Point" shall means a paper point

available to effectuate transfers of Gas from the Zone 1 Pooling

Point to Zone 2 (deemed located at the boundary of Zone 1 and Zone 2)

for contracting purposes only, which may be used as a primary receipt

point solely under a contract with firm capacity rights only in Zone

2. The Zone Boundary Transfer Point is available for the sole

purpose of effectuating transfers between the Zone 1 Pooling Point

and Zone 2 pursuant to Section 6.12(h) of the General Terms and

Conditions, and is not available for the receipt of Gas nominated

from any point in Zone 1 other than the Zone 1 Pooling Point.